Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Azamgarh | GAJA - SGIPL (JV) | 20087073 | JAMUN DEEH & JAGDEESHPUR CHAUR WATER SUPPLY SCHEME | 387.54 | 257.18 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 4 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 23 | 23 | No | 0 | NA | No | 22901.00 | 22901.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Azamgarh | Tarwan | Jagdeeshpur Chaur | 464423 | Jagdeeshpur Chaur | 140 | 140 | 100 | Har Gar Jal | Not Certified |
| 2 | Azamgarh | Tarwan | Jagdeeshpur Chaur | 464424 | Padri | 80 | 80 | 100 | Har Gar Jal | Not Certified |
| 3 | Azamgarh | Tarwan | Jamun Deeh | 464441 | Jamun Deeh | 170 | 160 | 94 | Work In Progress | Not Certified |
| 4 | Azamgarh | Tarwan | Jamun Deeh | 464442 | Rasulpur | 26 | 26 | 100 | Har Gar Jal | Not Certified |