Scheme Details
S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Approve By Agency Status | Approve By EE Status | Automation Status |
---|---|---|---|---|---|---|---|---|---|
1 | Mainpuri | NCC Ltd. | 20087105 | URTHAN + GAURI + NINOLI + SAHAS GRAM PANCHAYAT WATER SUPPLY SCHEME | 1550.84 | 802.83 | Verified | Verified | Not Integrated |
Scheme Assigne Villages
Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | Handed Over Villages |
---|---|---|---|---|---|---|---|---|---|---|---|
1 | Mainpuri | Barnahal | Urthan | 400266 | Urthan | 1117 | 1048 | 94 | Work In Progress | Not Certified | Not Verified |
2 | Mainpuri | Karhal | Ninoli | 400330 | Ninoli | 635 | 622 | 98 | Work In Progress | Not Certified | Not Verified |
3 | Mainpuri | Karhal | Gauri | 400336 | Gauri | 142 | 140 | 99 | Work In Progress | Not Certified | Not Verified |
4 | Mainpuri | Karhal | Gauri | 400337 | Nagla Madari | 120 | 117 | 98 | Work In Progress | Not Certified | Not Verified |
5 | Mainpuri | Karhal | Sahas | 400338 | Sahas | 229 | 229 | 100 | Har Gar Jal | Not Certified | Not Verified |
6 | Mainpuri | Karhal | Sahas | 400339 | Nagla Raja | 19 | 18 | 95 | Work In Progress | Not Certified | Not Verified |
Scheme Progress
Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
6 | 4 | 4 | 4 | 4 | 4 | 4 | 1 | 106 | 106 | Yes | 0 | NA | No | 84243.00 | 81200.00 |