Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Sant Kabeer Nagar | JAKSON - VISHVARAJ (JV) | 20087499 | LOUKIHA GP WSS | 219.30 | 128.52 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 3 | 1 | 1 | 1 | 1 | 1 | 0 | 0 | 16 | 16 | Yes | 0 | NA | No | 15046.00 | 15133.10 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Sant Kabeer Nagar | Pauli | Laukiha | 453195 | Rampur | 153 | 147 | 96 | Work In Progress | Not Certified |
| 2 | Sant Kabeer Nagar | Pauli | Laukiha | 453196 | Rupay Pur | 22 | 22 | 100 | Har Gar Jal | Not Certified |
| 3 | Sant Kabeer Nagar | Pauli | Laukiha | 453198 | Laukahiya | 147 | 147 | 100 | Har Gar Jal | Not Certified |