Scheme Details
S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Approve By Agency Status | Approve By EE Status | Automation Status |
---|---|---|---|---|---|---|---|---|---|
1 | Hathras | BGCCPL-Ramky (JV) | 20087520 | RASULPUR WATER SUPPLY SCHEME | 312.35 | 62.28 | Verified | Verified | Not Integrated |
Scheme Assigne Villages
Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | Handed Over Villages |
---|---|---|---|---|---|---|---|---|---|---|---|
1 | Hathras | Hasayan | Rasulpur | 396033 | Rasulpur | 154 | 118 | 77 | Work In Progress | Not Certified | Not Verified |
2 | Hathras | Hasayan | Rasulpur | 396034 | Ramnagria | 137 | 111 | 81 | Work In Progress | Not Certified | Not Verified |
3 | Hathras | Hasayan | Srinagar | 396042 | Srinagar | 105 | 105 | 100 | Har Gar Jal | Certified | Not Verified |
4 | Hathras | Hasayan | Srinagar | 396043 | Nagla Dali | 42 | 1 | 2 | Work In Progress | Not Certified | Not Verified |
5 | Hathras | Hasayan | Srinagar | 396044 | Garhi Birwal | 69 | 39 | 57 | Work In Progress | Not Certified | Not Verified |
Scheme Progress
Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
5 | 1 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | 0 | NA | 10 | NA | No | 13482.00 | 5000.00 |