Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Sant Kabeer Nagar | JAKSON - VISHVARAJ (JV) | 20087677 | SANICHARA BABOO & SANICHARA CHAUBEY GOV WSS | 270.00 | 132.15 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 7 | 1 | 1 | 1 | 1 | 1 | 0 | 0 | 20 | 20 | Yes | 0 | NA | No | 15228.00 | 12733.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Sant Kabeer Nagar | Nathnagar | Sanichara Baboo | 452886 | Sanichara Baboo | 155 | 155 | 100 | Har Gar Jal | Not Certified |
| 2 | Sant Kabeer Nagar | Nathnagar | Shanichara Chaubey | 452887 | Sanichara Chaubey | 59 | 51 | 86 | Work In Progress | Not Certified |
| 3 | Sant Kabeer Nagar | Nathnagar | Shanichara Chaubey | 452888 | Paldahajot Rukmena | 18 | 17 | 94 | Work In Progress | Not Certified |
| 4 | Sant Kabeer Nagar | Nathnagar | Shanichara Chaubey | 452889 | Paldhajot Milki | 42 | 23 | 55 | Work In Progress | Not Certified |
| 5 | Sant Kabeer Nagar | Nathnagar | Shanichara Chaubey | 452890 | Sanichara Pandey | 18 | 18 | 100 | Har Gar Jal | Not Certified |
| 6 | Sant Kabeer Nagar | Nathnagar | Shanichara Chaubey | 452891 | Reethijot | 39 | 31 | 79 | Work In Progress | Not Certified |
| 7 | Sant Kabeer Nagar | Nathnagar | Sanichara Baboo | 698301 | BELDUHA | 35 | 29 | 83 | Work In Progress | Not Certified |