Scheme Details
S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Approve By Agency Status | Approve By EE Status | Automation Status |
---|---|---|---|---|---|---|---|---|---|
1 | Bijnor | Vindhya-GAJA (JV) | 20088651 | Murtaja Nagar/ Gangadharpur Water Supply Scheme | 259.27 | 177.48 | Verified | Verified | Not Integrated |
Scheme Assigne Villages
Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | Handed Over Villages |
---|---|---|---|---|---|---|---|---|---|---|---|
1 | Bijnor | Budhanpur | Murtajanagar | 387286 | Murtajanagar | 250 | 250 | 100 | Har Gar Jal | Not Certified | Not Verified |
2 | Bijnor | Budhanpur | Murtajanagar | 387288 | Jamalpur Jat | 57 | 57 | 100 | Har Gar Jal | Not Certified | Not Verified |
3 | Bijnor | Budhanpur | Murtajanagar | 700332 | MIRAPUR | 36 | 36 | 100 | Har Gar Jal | Not Certified | Not Verified |
4 | Bijnor | Budhanpur | Murtajanagar | 700333 | TALAMPUR | 25 | 25 | 100 | Har Gar Jal | Not Certified | Not Verified |
Scheme Progress
Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
4 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 14 | 22 | Yes | 0 | NA | No | 7617.00 | 7527.80 |