Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Azamgarh | VIKRAN-VPRPL (JV) | 20089607 | USHARI KHURAMPUR,MUFTIPUR | 171.43 | 80.85 | Not Integrated | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 2 | 1 | 1 | 1 | 1 | 1 | 0 | 0 | 13 | 13 | Yes | 0 | NA | No | 5943.00 | 5294.00 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Azamgarh | Tekma | Usari Khurampur | 464165 | Muktipur | 66 | 65 | 98 | Work In Progress | Not Certified | 
| 2 | Azamgarh | Tekma | Usari Khurampur | 464166 | Usari Khurrampur | 118 | 118 | 100 | Har Gar Jal | Not Certified |