Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Azamgarh | M/s Sudhakara Infratech Pvt. Ltd | 20089627 | KADIPUR USARI AND BASTI | 272.90 | 141.12 | view more | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 3 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 16 | 20 | Yes | 0 | NA | No | 11752.00 | 8233.00 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Azamgarh | Sathiyaon | Kadipur Usari | 463025 | Kadi Pur Usari | 141 | 128 | 91 | Work In Progress | Not Certified | 
| 2 | Azamgarh | Sathiyaon | Basti | 463026 | Basti | 147 | 142 | 97 | Work In Progress | Not Certified | 
| 3 | Azamgarh | Sathiyaon | Basti | 463027 | Chak Basti | 13 | 11 | 85 | Work In Progress | Not Certified |