Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Azamgarh | M/s Sudhakara Infratech Pvt. Ltd | 20089685 | NETPUR & MOHIUDDINPUR water supply scheme | 365.80 | 121.43 | Not Integrated | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 6 | 1 | 1 | 1 | 1 | 1 | 0 | 0 | 27 | 27 | Yes | 0 | NA | No | 18671.00 | 17230.00 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Azamgarh | Jahanaganj | Netpur | 463141 | Padar Vochh Or Padar Pokh | 180 | 171 | 95 | Work In Progress | Not Certified | 
| 2 | Azamgarh | Jahanaganj | Netpur | 463241 | Netpur | 322 | 314 | 98 | Work In Progress | Not Certified | 
| 3 | Azamgarh | Jahanaganj | Netpur | 463300 | Mak Raudha Khurd | 69 | 65 | 94 | Work In Progress | Not Certified | 
| 4 | Azamgarh | Jahanaganj | Netpur | 463307 | Mubarakpur Urf Vinashpur Or Di | 98 | 93 | 95 | Work In Progress | Not Certified | 
| 5 | Azamgarh | Jahanaganj | Mohiuddinpur | 463309 | Mohiuddinpur | 103 | 99 | 96 | Work In Progress | Not Certified | 
| 6 | Azamgarh | Jahanaganj | Mohiuddinpur | 680484 | Mudan Chak | 8 | 3 | 38 | Work In Progress | Not Certified |