Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Shravasti | GA INFRA-VPL | 20089758 | ETAUNJHA_BARAIPUR | 444.57 | 132.73 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 2 | 1 | 1 | 1 | 1 | 1 | 0 | 0 | 27 | 0 | NA | 0 | NA | No | 24868.00 | 17597.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Shravasti | Ekona | Baraipur | 443433 | Baraipur | 239 | 230 | 96 | Work In Progress | Not Certified |
| 2 | Shravasti | Ekona | Etaunjha | 443438 | Etaunjha | 331 | 321 | 97 | Work In Progress | Not Certified |