Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Etawah | OMIL-JWIL (JV) | 20091624 | CHHIBROLI & KUNDOL | 321.41 | 143.50 | Not Integrated | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 4 | 1 | 1 | 1 | 1 | 1 | 0 | 0 | 30 | 30 | Yes | 0 | NA | No | 19247.00 | 18990.00 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Etawah | Chakkarnagar | Kundol | 420103 | Palighar | 211 | 207 | 98 | Work In Progress | Not Certified | 
| 2 | Etawah | Chakkarnagar | Chhibroli | 420111 | Kainchhi | 100 | 95 | 95 | Work In Progress | Not Certified | 
| 3 | Etawah | Chakkarnagar | Chhibroli | 420112 | Gopalpur | 114 | 103 | 90 | Work In Progress | Not Certified | 
| 4 | Etawah | Chakkarnagar | Chhibroli | 420113 | Chhibroli | 145 | 144 | 99 | Work In Progress | Not Certified |