Scheme Details
S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Approve By Agency Status | Approve By EE Status | Automation Status |
---|---|---|---|---|---|---|---|---|---|
1 | Ayodhya | VSA | 20091983 | MANGREE WSS | 934.15 | 656.96 | Verified | Verified | Not Integrated |
Scheme Assigne Villages
Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | Handed Over Villages |
---|---|---|---|---|---|---|---|---|---|---|---|
1 | Ayodhya | Bikapur | Asrewa | 437267 | Asrewa | 268 | 268 | 100 | Har Gar Jal | Not Certified | Not Verified |
2 | Ayodhya | Bikapur | Mangaree | 437269 | Mangaree | 222 | 222 | 100 | Har Gar Jal | Not Certified | Not Verified |
3 | Ayodhya | Bikapur | Mangaree | 677770 | Haribansh Pur | 28 | 28 | 100 | Har Gar Jal | Not Certified | Not Verified |
4 | Ayodhya | Bikapur | Mangaree | 677771 | Kurebhari | 133 | 133 | 100 | Har Gar Jal | Not Certified | Not Verified |
5 | Ayodhya | Bikapur | Mangaree | 677772 | Pratappur Urf Barhupur | 33 | 33 | 100 | Har Gar Jal | Not Certified | Not Verified |
Scheme Progress
Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
5 | 2 | 2 | 2 | 2 | 1 | 1 | 0 | 58 | 58 | NA | 0 | NA | No | 58338.00 | 41251.00 |