Scheme Details
DISTRICT
Azamgarh
AGENCY
M/s Sudhakara Infratech Pvt. Ltd
SCHEME ID
20092102
SCHEME NAME
KOLOHUKHOR WATER SUPPLY SCHEME
ESTIMATED COST
493.66
EXPENDITURE
388.50
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Operation & Maintenance
Scheme Physical Progress
Village Coverage
Village Covered
6
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
0
Work Completed
1
Solar Plant
Required
37
Procured
37
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
29316.00
Meter
Length Laid
29176.00
Meter
Scheme Assigned Villages
8 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Azamgarh | Jahanaganj | KOLOHUKHOR | 463133 | Muzaffarpur | 18 | 16 | 89% | Work In Progress | Not Certified |
| 2 | Azamgarh | Jahanaganj | KOLOHUKHOR | 463140 | Shyam Chak | 58 | 54 | 93% | Work In Progress | Not Certified |
| 3 | Azamgarh | Jahanaganj | KOLOHUKHOR | 463218 | Karaut | 407 | 398 | 98% | Work In Progress | Not Certified |
| 4 | Azamgarh | Jahanaganj | KOLOHUKHOR | 463219 | Naiyanpur | 242 | 236 | 98% | Work In Progress | Not Certified |
| 5 | Azamgarh | Jahanaganj | KOLOHUKHOR | 463236 | Kolohukhor | 298 | 291 | 98% | Work In Progress | Not Certified |
| 6 | Azamgarh | Jahanaganj | KOLOHUKHOR | 680445 | Sundar Chak | 9 | 1 | 11% | Work In Progress | Not Certified |
| 7 | Azamgarh | Jahanaganj | KOLOHUKHOR | 696068 | KADIPUR | 45 | 38 | 84% | Work In Progress | Not Certified |
| 8 | Azamgarh | Jahanaganj | KOLOHUKHOR | 702922 | KULHUKHOR | 66 | 57 | 86% | Work In Progress | Not Certified |