Scheme Details
S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Approve By Agency Status | Approve By EE Status | Automation Status |
---|---|---|---|---|---|---|---|---|---|
1 | Ayodhya | Vindhya-GAJA (JV) | 20092282 | RAMNAGAR & RATANPUR TENDUA WSS | 574.50 | 343.47 | Verified | Verified | Not Integrated |
Scheme Assigne Villages
Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | Handed Over Villages |
---|---|---|---|---|---|---|---|---|---|---|---|
1 | Ayodhya | Bikapur | Ram Nagar | 437229 | Basupur | 37 | 37 | 100 | Har Gar Jal | Not Certified | Not Verified |
2 | Ayodhya | Bikapur | Ram Nagar | 437230 | Ram Nagar | 414 | 414 | 100 | Har Gar Jal | Not Certified | Not Verified |
3 | Ayodhya | Bikapur | RATAN PUR TENDUA | 437274 | NUBAWAN VAIDARA | 33 | 30 | 91 | Work In Progress | Not Certified | Not Verified |
4 | Ayodhya | Bikapur | RATAN PUR TENDUA | 437275 | Ratanpur Tendua | 89 | 89 | 100 | Har Gar Jal | Not Certified | Not Verified |
Scheme Progress
Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
4 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 28 | 28 | Yes | 0 | NA | No | 37160.00 | 34070.00 |