Scheme Details
S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Approve By Agency Status | Approve By EE Status | Automation Status |
---|---|---|---|---|---|---|---|---|---|
1 | Ayodhya | Vindhya-GAJA (JV) | 20092335 | GOTHAURA WSS | 535.85 | 322.95 | Verified | Verified | Not Integrated |
Scheme Assigne Villages
Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | Handed Over Villages |
---|---|---|---|---|---|---|---|---|---|---|---|
1 | Ayodhya | Tarun | Gothaura | 437433 | Gothora | 126 | 126 | 100 | Har Gar Jal | Not Certified | Not Verified |
2 | Ayodhya | Tarun | Gothaura | 437435 | VELA CHAKSIRAM | 85 | 85 | 100 | Har Gar Jal | Not Certified | Not Verified |
3 | Ayodhya | Tarun | Hathigo | 437442 | Hathigo | 627 | 627 | 100 | Har Gar Jal | Not Certified | Not Verified |
Scheme Progress
Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
3 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 28 | 28 | Yes | 0 | NA | No | 32661.00 | 27300.00 |