Scheme Details
S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Approve By Agency Status | Approve By EE Status | Automation Status |
---|---|---|---|---|---|---|---|---|---|
1 | Mainpuri | NCC Ltd. | 20094476 | BIDHUNA + KUAKHEDA + JAWAPUR GRAM PANCHAYAT WATER SUPPLY SCHEME | 1061.59 | 584.13 | Verified | Verified | Not Integrated |
Scheme Assigne Villages
Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | Handed Over Villages |
---|---|---|---|---|---|---|---|---|---|---|---|
1 | Mainpuri | Ghiror | Bidhuna | 400020 | Bidhuna | 260 | 252 | 97 | Work In Progress | Not Certified | Not Verified |
2 | Mainpuri | Mainpuri | Kuakheda | 400197 | Kuakheda | 62 | 60 | 97 | Work In Progress | Not Certified | Not Verified |
3 | Mainpuri | Mainpuri | Kuakheda | 400198 | Divauli | 117 | 115 | 98 | Work In Progress | Not Certified | Not Verified |
4 | Mainpuri | Mainpuri | Kuakheda | 400199 | Jat Khera | 76 | 74 | 97 | Work In Progress | Not Certified | Not Verified |
5 | Mainpuri | Mainpuri | Kuakheda | 400200 | Jichauli | 29 | 28 | 97 | Work In Progress | Not Certified | Not Verified |
6 | Mainpuri | Mainpuri | Jawapur | 400203 | Jawapur | 1009 | 977 | 97 | Work In Progress | Not Certified | Not Verified |
Scheme Progress
Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
6 | 4 | 4 | 4 | 4 | 3 | 2 | 0 | 10 | 10 | Yes | 0 | NA | No | 46924.00 | 46820.00 |