Scheme Details
S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Approve By Agency Status | Approve By EE Status | Automation Status |
---|---|---|---|---|---|---|---|---|---|
1 | Jaunpur | AFCONS | 20095015 | KALINJARA & BRAHMANPUR NAVABAD VILLAGE WATER SUPPLY SCHEME | 565.46 | 304.75 | Verified | Verified | view more |
Scheme Assigne Villages
Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | Handed Over Villages |
---|---|---|---|---|---|---|---|---|---|---|---|
1 | Jaunpur | Baksha | Kalinjara | 469059 | Basara | 154 | 154 | 100 | Har Gar Jal | Certified | Not Verified |
2 | Jaunpur | Baksha | Kalinjara | 469060 | Kalinjara | 265 | 265 | 100 | Har Gar Jal | Certified | Not Verified |
3 | Jaunpur | Baksha | Brahmanpur Navabad | 469061 | Saraule | 119 | 119 | 100 | Har Gar Jal | Certified | Not Verified |
4 | Jaunpur | Baksha | Brahmanpur Navabad | 469062 | Brahmanpur Navabad | 235 | 235 | 100 | Har Gar Jal | Not Certified | Not Verified |
Scheme Progress
Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
4 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 37 | 37 | Yes | 0 | NA | No | 49597.00 | 41447.00 |