Follow us on for latest updates.    |    To Lodge Complaint Call On 18001212164   or   visit   www.jalsamadhan.in


Scheme Details

S.No. District Name Agency Name Scheme Id Scheme Name Estimated Cost Expenditure Approve By Agency Status Approve By EE Status Automation Status
1 Prayagraj Larsen & Toubro Ltd 20095033 RAMPUR URF BALRAMPUR_MANDAUR WATER SUPPLY SCHEME 388.50 144.21 Verified Verified Not Integrated

Scheme Assigne Villages

Sno. District Name Bolck Panchayat Village ID Village Name House Holds FHTC FHTC % Har Gar Jal Certified Handed Over Villages
1 Prayagraj Bahadurpur Mandaur 432537 Mandaur 659 651 99 Work In Progress Not Certified Not Verified
2 Prayagraj Bahadurpur Rampur Urf Balrampur 432551 Rampur Urf Balrampur 279 265 95 Work In Progress Not Certified Not Verified

Scheme Progress

Village Covered T/W OHT Solar Plant Electric Distribution (Line Laying in meter.)
Required Boring Done Air Compressor done O. P. Unit done Required Work Started Work Completed Required Procured (KW) Work status Required Transformer Procured Work status Total Length Length Laid
2 1 1 1 1 1 1 0 42 42 No 0 NA No 21659.00 21600.00