Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Azamgarh | M/s Sudhakara Infratech Pvt. Ltd | 20095038 | ASARAFPUR Water supply scheme | 286.72 | 150.35 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 2 | 1 | 1 | 1 | 1 | 1 | 0 | 1 | 18 | 18 | Yes | 0 | NA | No | 10647.00 | 9756.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Azamgarh | Bilariaganj | Asaraf Pur | 462055 | Asaraf Pur | 420 | 405 | 96 | Work In Progress | Not Certified |
| 2 | Azamgarh | Bilariaganj | Asaraf Pur | 462056 | Bibepur | 6 | 1 | 17 | Work In Progress | Not Certified |