Scheme Details
S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Approve By Agency Status | Approve By EE Status | Automation Status |
---|---|---|---|---|---|---|---|---|---|
1 | Siddharth Nagar | JAKSON - VISHVARAJ (JV) | 20095114 | BABHANI AND TRILOKPUR GP WSS | 459.72 | 136.40 | Verified | Verified | Not Integrated |
Scheme Assigne Villages
Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | Handed Over Villages |
---|---|---|---|---|---|---|---|---|---|---|---|
1 | Siddharth Nagar | Bhanwapur | Babhani | 447956 | Manoharpur | 108 | 14 | 13 | Work In Progress | Not Certified | Not Verified |
2 | Siddharth Nagar | Bhanwapur | Trilokpur | 447959 | Trilokpur | 130 | 15 | 12 | Work In Progress | Not Certified | Not Verified |
3 | Siddharth Nagar | Bhanwapur | Babhani | 447964 | Baur Dih | 79 | 10 | 13 | Work In Progress | Not Certified | Not Verified |
4 | Siddharth Nagar | Bhanwapur | Babhani | 447965 | Babhani | 264 | 263 | 100 | Work In Progress | Not Certified | Not Verified |
Scheme Progress
Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
4 | 1 | 1 | 1 | 1 | 1 | 0 | 0 | 30 | 30 | Yes | 0 | NA | No | 16266.00 | 16200.00 |