Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Azamgarh | M/s Sudhakara Infratech Pvt. Ltd | 20095132 | ISARPAR KHAS Water supply scheme | 236.76 | 114.00 | Not Integrated | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 7 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 16 | 16 | NA | 0 | NA | No | 12536.00 | 9072.00 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Azamgarh | Tahbarpur | Isarpar Khas | 462592 | Nakhipur | 8 | 5 | 62 | Work In Progress | Not Certified | 
| 2 | Azamgarh | Tahbarpur | Isarpar Khas | 462593 | Yadav Pur | 7 | 7 | 100 | Har Gar Jal | Not Certified | 
| 3 | Azamgarh | Tahbarpur | Isarpar Khas | 462594 | Palia Khas | 31 | 22 | 71 | Work In Progress | Not Certified | 
| 4 | Azamgarh | Tahbarpur | Isarpar Khas | 462595 | Chaturpur | 29 | 29 | 100 | Har Gar Jal | Not Certified | 
| 5 | Azamgarh | Tahbarpur | Isarpar Khas | 462596 | Zameen Palia | 10 | 10 | 100 | Har Gar Jal | Not Certified | 
| 6 | Azamgarh | Tahbarpur | Isarpar Khas | 462597 | Bibalpur | 20 | 20 | 100 | Har Gar Jal | Not Certified | 
| 7 | Azamgarh | Tahbarpur | Isarpar Khas | 462598 | Isarpar Khas | 141 | 139 | 99 | Work In Progress | Not Certified |