Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Siddharth Nagar | VSA | 20095148 | MANOHARI AND SABUA JOGIYA GP WSS | 290.03 | 89.98 | Not Integrated | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 4 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 23 | 23 | Yes | 0 | NA | No | 10056.00 | 10056.00 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Siddharth Nagar | Naugarh | Manohari | 446743 | Banarahi | 69 | 53 | 77 | Work In Progress | Not Certified | 
| 2 | Siddharth Nagar | Naugarh | Manohari | 446744 | Manohari | 157 | 135 | 86 | Work In Progress | Not Certified | 
| 3 | Siddharth Nagar | Jogia Khas | Sabui Sabua | 446856 | Sabui | 167 | 151 | 90 | Work In Progress | Not Certified | 
| 4 | Siddharth Nagar | Jogia Khas | Sabui Sabua | 446857 | Sabua | 105 | 100 | 95 | Work In Progress | Not Certified |