Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Azamgarh | GAJA - SGIPL (JV) | 20095325 | DAVNATHPUR,BASHI | 549.03 | 216.36 | Not Integrated | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 6 | 1 | 1 | 1 | 1 | 1 | 0 | 0 | 37 | 37 | Yes | 0 | NA | No | 24382.00 | 24382.00 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Azamgarh | Lalganj | Devnathpur | 464281 | Isemiyelpur | 62 | 8 | 13 | Work In Progress | Not Certified | 
| 2 | Azamgarh | Lalganj | Devnathpur | 464282 | Davnathpur | 83 | 9 | 11 | Work In Progress | Not Certified | 
| 3 | Azamgarh | Lalganj | Bashi | 464374 | Bashi | 306 | 123 | 40 | Work In Progress | Not Certified | 
| 4 | Azamgarh | Lalganj | Bashi | 464375 | Akbal Pur | 59 | 24 | 41 | Work In Progress | Not Certified | 
| 5 | Azamgarh | Lalganj | Bashi | 464376 | Chak Basadi | 4 | 1 | 25 | Work In Progress | Not Certified | 
| 6 | Azamgarh | Lalganj | Bashi | 464377 | Chak Jamal Kamal | 1 | 1 | 100 | Har Gar Jal | Not Certified |