Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Azamgarh | LC INFRA | 20096371 | SARAY VRINDAVAN Water SUPPLY | 184.82 | 98.65 | Not Integrated | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 4 | 1 | 1 | 1 | 1 | 1 | 0 | 0 | 16 | 16 | NA | 0 | NA | No | 9227.00 | 8551.00 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Azamgarh | Tarwan | Saray Vrindavan | 464537 | Saray Vrindavan | 251 | 245 | 98 | Work In Progress | Not Certified | 
| 2 | Azamgarh | Tarwan | Saray Vrindavan | 464538 | Murar Pur | 142 | 127 | 89 | Work In Progress | Not Certified | 
| 3 | Azamgarh | Tarwan | Saray Vrindavan | 464539 | Karnaipur | 6 | 1 | 17 | Work In Progress | Not Certified | 
| 4 | Azamgarh | Tarwan | Saray Vrindavan | 464540 | Nimdipur | 1 | 1 | 100 | Har Gar Jal | Not Certified |