Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Siddharth Nagar | JAKSON - VISHVARAJ (JV) | 20096572 | BELHASA SECOND GP WSS | 206.42 | 55.59 | Not Integrated | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 3 | 1 | 1 | 1 | 1 | 1 | 0 | 0 | 16 | 16 | NA | 0 | NA | No | 5256.00 | 5200.00 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Siddharth Nagar | Itwa | Belhasa Second | 448208 | Belhasa | 195 | 65 | 33 | Work In Progress | Not Certified | 
| 2 | Siddharth Nagar | Itwa | Belhasa Second | 448209 | Pali | 51 | 35 | 69 | Work In Progress | Not Certified | 
| 3 | Siddharth Nagar | Itwa | Belhasa Second | 656427 | Pakadi | 172 | 2 | 1 | Work In Progress | Not Certified |