Scheme Details
S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Approve By Agency Status | Approve By EE Status | Automation Status |
---|---|---|---|---|---|---|---|---|---|
1 | Siddharth Nagar | JAKSON - VISHVARAJ (JV) | 20096681 | BHAISAHAWA GP WSS | 291.07 | 82.56 | Verified | Verified | Not Integrated |
Scheme Assigne Villages
Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | Handed Over Villages |
---|---|---|---|---|---|---|---|---|---|---|---|
1 | Siddharth Nagar | Jogia Khas | Bhaisahawa | 446877 | Bhaisahawa | 208 | 206 | 99 | Work In Progress | Not Certified | Not Verified |
2 | Siddharth Nagar | Jogia Khas | Bhaisahawa | 446878 | Bhat Purawa | 69 | 68 | 99 | Work In Progress | Not Certified | Not Verified |
3 | Siddharth Nagar | Jogia Khas | Bhaisahawa | 446879 | Parasohiya | 108 | 107 | 99 | Work In Progress | Not Certified | Not Verified |
Scheme Progress
Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
3 | 1 | 1 | 1 | 1 | 1 | 0 | 0 | 23 | 23 | Yes | 0 | NA | No | 11396.00 | 11300.00 |