Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Siddharth Nagar | JAKSON - VISHVARAJ (JV) | 20096741 | KOLHUA FIRST AND SUGAHI GP WSS | 241.86 | 150.88 | view more | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 2 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 16 | 16 | Yes | 0 | NA | No | 10187.00 | 10050.00 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Siddharth Nagar | Uska Bazar | Sugahi | 447112 | Sugahi | 220 | 220 | 100 | Har Gar Jal | Not Certified | 
| 2 | Siddharth Nagar | Uska Bazar | Kolhua First | 447125 | Kolhua | 246 | 223 | 91 | Work In Progress | Not Certified | 
| 3 | Siddharth Nagar | Uska Bazar | Kolhua First | 695814 | KHAIRA | 52 | 0 | 0 | Work In Progress | Not Certified | 
| 4 | Siddharth Nagar | Uska Bazar | Kolhua First | 696439 | UTAPAR | 16 | 0 | 0 | Work In Progress | Not Certified | 
| 5 | Siddharth Nagar | Uska Bazar | Kolhua First | 698255 | BHAISAHIYA | 26 | 0 | 0 | Work In Progress | Not Certified | 
| 6 | Siddharth Nagar | Uska Bazar | Kolhua First | 698330 | SARANGI | 70 | 0 | 0 | Work In Progress | Not Certified |