Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Siddharth Nagar | JAKSON - VISHVARAJ (JV) | 20096755 | PARSOHIYA AND PARSA DIVAN GP WSS | 316.37 | 108.48 | Not Integrated | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 3 | 1 | 1 | 1 | 1 | 1 | 0 | 0 | 23 | 23 | Yes | 0 | NA | No | 11865.00 | 11800.00 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Siddharth Nagar | Barhni | Parsohiya | 446390 | Parsohiya | 145 | 108 | 74 | Work In Progress | Not Certified | 
| 2 | Siddharth Nagar | Barhni | Parsa Diwan | 446430 | Parsa Divan | 238 | 134 | 56 | Work In Progress | Not Certified | 
| 3 | Siddharth Nagar | Barhni | Parsohiya | 446431 | Shivpur Lagani | 1 | 1 | 100 | Har Gar Jal | Not Certified |