Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Siddharth Nagar | JAKSON - VISHVARAJ (JV) | 20096823 | MISHROLIYA MAFI AND MAHUWA KHURD GP WSS | 351.15 | 130.95 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 3 | 1 | 1 | 1 | 1 | 1 | 0 | 0 | 23 | 23 | NA | 0 | NA | No | 14517.00 | 14513.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Siddharth Nagar | Domariyaganj | Mishroliya Mafi | 448461 | MISHRAULIYA MAUFI | 985 | 350 | 36 | Work In Progress | Not Certified |
| 2 | Siddharth Nagar | Domariyaganj | Mahuwa Khurd | 448464 | Mahuwakhurd | 200 | 199 | 100 | Work In Progress | Not Certified |
| 3 | Siddharth Nagar | Domariyaganj | Mahuwa Khurd | 448465 | Mahuwa Buzurg | 90 | 77 | 86 | Work In Progress | Not Certified |
| 4 | Siddharth Nagar | Domariyaganj | Mishroliya Mafi | 696442 | Ekgharwa | 9 | 0 | 0 | Work In Progress | Not Certified |