Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Shravasti | GA INFRA-VPL | 20097318 | DHANNIDIH _ SARRA BOJHI | 520.68 | 137.65 | Not Integrated | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 2 | 2 | 1 | 1 | 1 | 1 | 0 | 0 | 32 | 0 | NA | 0 | NA | No | 23975.00 | 19255.00 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Shravasti | Sirsiya | Dhannidih | 443216 | Dhannidih | 314 | 309 | 98 | Work In Progress | Not Certified | 
| 2 | Shravasti | Sirsiya | Sarra Bojhi | 443219 | Sarra Bojhi | 399 | 394 | 99 | Work In Progress | Not Certified |