Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Kaushambi | JMC - Lakshmi (JV) | 20098077 | BARAI BANDHAWA GAUHANI GOV GPWSS | 512.26 | 146.78 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 4 | 1 | 1 | 1 | 1 | 1 | 0 | 0 | 0 | 0 | NA | 13 | NA | No | 21720.00 | 19980.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Kaushambi | Kaushambi | Barai Bandhawa | 431281 | Barai Bandhawa | 490 | 423 | 86 | Work In Progress | Not Certified |
| 2 | Kaushambi | Kaushambi | Gouhani | 431282 | Malipur Urf Mahraj Ganj | 144 | 69 | 48 | Work In Progress | Not Certified |
| 3 | Kaushambi | Kaushambi | Gouhani | 431283 | Akoura | 116 | 94 | 81 | Work In Progress | Not Certified |
| 4 | Kaushambi | Kaushambi | Gouhani | 431284 | Gouhani | 103 | 90 | 87 | Work In Progress | Not Certified |