Scheme Details
S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Approve By Agency Status | Approve By EE Status | Automation Status |
---|---|---|---|---|---|---|---|---|---|
1 | Balrampur | Larsen & Toubro Ltd | 20098106 | ALLAH NAGAR WATER SUPPLY SCHEME | 272.65 | 100.14 | Verified | Verified | Not Integrated |
Scheme Assigne Villages
Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | Handed Over Villages |
---|---|---|---|---|---|---|---|---|---|---|---|
1 | Balrampur | Utraula | Allah Nager | 444258 | Allah Nager | 208 | 208 | 100 | Har Gar Jal | Certified | Not Verified |
2 | Balrampur | Utraula | Allah Nager | 444259 | Bagahia | 10 | 10 | 100 | Har Gar Jal | Certified | Not Verified |
3 | Balrampur | Utraula | Allah Nager | 444260 | Faguia | 70 | 70 | 100 | Har Gar Jal | Certified | Not Verified |
4 | Balrampur | Utraula | Allah Nager | 444261 | Tilher | 42 | 42 | 100 | Har Gar Jal | Certified | Not Verified |
5 | Balrampur | Utraula | Allah Nager | 444262 | Januki | 60 | 60 | 100 | Har Gar Jal | Certified | Not Verified |
Scheme Progress
Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
5 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 16 | 16 | Yes | 0 | NA | No | 13641.00 | 13641.00 |