Scheme Details
S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Approve By Agency Status | Approve By EE Status | Automation Status |
---|---|---|---|---|---|---|---|---|---|
1 | Kushi Nagar | NCC Ltd. | 20099075 | SHIVPUR | 423.89 | 128.70 | Verified | Not Verified | Not Integrated |
Scheme Assigne Villages
Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | Handed Over Villages |
---|---|---|---|---|---|---|---|---|---|---|---|
1 | Kushi Nagar | Khadda | Narayan Pur | 457481 | Bakuladah | 63 | 25 | 40 | Work In Progress | Not Certified | Not Verified |
2 | Kushi Nagar | Khadda | Narayan Pur | 457482 | Narainpur | 377 | 377 | 100 | Har Gar Jal | Not Certified | Not Verified |
3 | Kushi Nagar | Khadda | Hariharpur | 457483 | Hariharpur | 167 | 167 | 100 | Har Gar Jal | Not Certified | Not Verified |
4 | Kushi Nagar | Khadda | Shivpur | 457484 | Shivpur | 295 | 295 | 100 | Har Gar Jal | Certified | Not Verified |
Scheme Progress
Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
4 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 30 | 27 | NA | 0 | NA | No | 9500.00 | 9500.00 |