S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Approve By Agency Status | Approve By EE Status | Automation Status |
---|---|---|---|---|---|---|---|---|---|
1 | Deoria | LC INFRA | 20099215 | RO-REORGANISATION OF GAURI BAZAR GROUP OF VILLAGES WATER SUPPLY SCHEME | 496.21 | 368.01 | Verified | Verified | view more |
Scheme Assigne Villages
Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | Handed Over Villages |
---|---|---|---|---|---|---|---|---|---|---|---|
1 | Deoria | Gauri Bazar | Mathia | 459226 | Mathia | 372 | 372 | 100 | Har Gar Jal | Certified | Not Verified |
2 | Deoria | Gauri Bazar | Pathar Hat | 459278 | Pathar Hat | 1115 | 1115 | 100 | Har Gar Jal | Not Certified | Not Verified |
3 | Deoria | Gauri Bazar | Pathar Hat | 459279 | Karkathi | 8 | 8 | 100 | Har Gar Jal | Not Certified | Not Verified |
Scheme Progress
Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
3 | 2 | 2 | 2 | 2 | 1 | 1 | 1 | 0 | 0 | NA | 25 | NA | No | 22074.00 | 22000.00 |