Track Your Scheme

Scheme Details
DISTRICT Sitapur
AGENCY NCC Ltd.
SCHEME ID 20099528
SCHEME NAME Baddapur & Chhaheliya Water Supply Scheme
ESTIMATED COST 364.11
EXPENDITURE 201.62
AUTOMATION STATUS Not Integrated
SCHEME STATUS Under Construction
Scheme Physical Progress
Village Coverage
Village Covered 3
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 1
Work Completed 0
Solar Plant
Required 28
Procured 28 KW
Work Status Yes
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 12759.00 Meter
Length Laid 11921.00 Meter

Scheme Assigned Villages

3 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Sitapur Pisawan Baddapur 409522 Amanullapur 178 177 99% Work In Progress Not Certified
2 Sitapur Pisawan Baddapur 409523 Baddapur 192 189 98% Work In Progress Not Certified
3 Sitapur Pisawan Chhaheliya 409545 Chhaheliya 327 325 99% Work In Progress Not Certified