Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Kanpur Dehat | VSA | 20099647 | Girdaun | 321.48 | 161.19 | Not Integrated | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 2 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 37 | 37 | Yes | 0 | NA | No | 10689.00 | 10689.00 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Kanpur Dehat | Malasa | Girdaun | 421606 | Girdaun | 419 | 419 | 100 | Har Gar Jal | Certified | 
| 2 | Kanpur Dehat | Malasa | Girdaun | 421607 | Akabarnagar | 238 | 238 | 100 | Har Gar Jal | Certified |