Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Siddharth Nagar | VSA | 20099659 | ITWA BAKSI & PIPRI BUJURG & SUHEELWA WSS | 617.00 | 207.17 | Not Integrated | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 6 | 2 | 2 | 2 | 2 | 1 | 1 | 1 | 58 | 58 | Yes | 0 | NA | No | 18602.00 | 18254.00 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Siddharth Nagar | Itwa | Pipri Bujurg | 448193 | Pipri Bujurg | 310 | 301 | 97 | Work In Progress | Not Certified | 
| 2 | Siddharth Nagar | Itwa | Itwa Baksi | 448194 | Itwa Baksi | 251 | 251 | 100 | Har Gar Jal | Not Certified | 
| 3 | Siddharth Nagar | Itwa | Itwa Baksi | 448195 | Pipri Lagri | 54 | 50 | 93 | Work In Progress | Not Certified | 
| 4 | Siddharth Nagar | Itwa | Itwa Baksi | 448196 | Mudila Vish Datt | 146 | 144 | 99 | Work In Progress | Not Certified | 
| 5 | Siddharth Nagar | Itwa | Suhelwa | 448198 | Suhelwa | 173 | 146 | 84 | Work In Progress | Not Certified | 
| 6 | Siddharth Nagar | Itwa | Itwa Baksi | 656492 | Nauwagav | 178 | 171 | 96 | Work In Progress | Not Certified |