Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Siddharth Nagar | VSA | 20099660 | KALANIYA & KARHIYA GOSHAI | 379.43 | 153.42 | Not Integrated | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 5 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 27 | 27 | Yes | 0 | NA | No | 17578.00 | 17520.00 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Siddharth Nagar | Khuniyaon | Karhiya Goshai | 448322 | Karhiya Goshai | 105 | 105 | 100 | Har Gar Jal | Not Certified | 
| 2 | Siddharth Nagar | Khuniyaon | Karhiya Goshai | 448323 | Dhaurahra | 47 | 38 | 81 | Work In Progress | Not Certified | 
| 3 | Siddharth Nagar | Khuniyaon | Karhiya Goshai | 448324 | Darsaniya | 109 | 97 | 89 | Work In Progress | Not Certified | 
| 4 | Siddharth Nagar | Khuniyaon | Kalyaniya | 448325 | Kalyaniya | 158 | 158 | 100 | Har Gar Jal | Not Certified | 
| 5 | Siddharth Nagar | Khuniyaon | Kalyaniya | 448326 | Navel | 78 | 71 | 91 | Work In Progress | Not Certified |