Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Etawah | OMIL-JWIL (JV) | 20099912 | KISHONPUR JADONPUR | 211.87 | 55.34 | Not Integrated | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 4 | 1 | 1 | 1 | 1 | 0 | 0 | 0 | 0 | 0 | NA | 12 | NA | No | 9997.00 | 9500.00 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Etawah | Badapura | Kishonpur Jadonpur | 419717 | Kishonpur Jadonpur | 214 | 207 | 97 | Work In Progress | Not Certified | 
| 2 | Etawah | Badapura | Kishonpur Jadonpur | 419718 | Aarazi Jadhonpur | 94 | 90 | 96 | Work In Progress | Not Certified | 
| 3 | Etawah | Badapura | Kishonpur Jadonpur | 419719 | Jadhonpur | 87 | 83 | 95 | Work In Progress | Not Certified | 
| 4 | Etawah | Badapura | Kishonpur Jadonpur | 419720 | Rampur Naoli | 214 | 205 | 96 | Work In Progress | Not Certified |