Scheme Details
S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Approve By Agency Status | Approve By EE Status | Automation Status |
---|---|---|---|---|---|---|---|---|---|
1 | Mau | GA INFRA-VPL | 20100987 | GANGUWABARI & TIGHARA GRAM PANCHAYAT WATER SUPPLY SCHEME | 329.77 | 249.36 | Verified | Verified | Not Integrated |
Scheme Assigne Villages
Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | Handed Over Villages |
---|---|---|---|---|---|---|---|---|---|---|---|
1 | Mau | Kopaganj | Tidhara | 465623 | Tighara | 296 | 296 | 100 | Har Gar Jal | Certified | Not Verified |
2 | Mau | Kopaganj | Ganguwabari | 465624 | Bhairopur | 139 | 139 | 100 | Har Gar Jal | Certified | Not Verified |
3 | Mau | Kopaganj | Ganguwabari | 697556 | GANGUABAARI | 200 | 200 | 100 | Har Gar Jal | Certified | Not Verified |
Scheme Progress
Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
3 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 20 | 20 | Yes | 0 | NA | No | 25762.00 | 25530.00 |