Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Siddharth Nagar | VSA | 20101595 | BASAWANPUR & NAGAWA WSS | 362.37 | 106.09 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 4 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 27 | 27 | Yes | 0 | NA | No | 10484.00 | 10484.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Siddharth Nagar | Uska Bazar | Basawanpur | 447017 | Basawanpur | 111 | 111 | 100 | Har Gar Jal | Not Certified |
| 2 | Siddharth Nagar | Uska Bazar | Basawanpur | 447018 | Kara Chhuliya Khalasa | 125 | 107 | 86 | Work In Progress | Not Certified |
| 3 | Siddharth Nagar | Uska Bazar | Basawanpur | 447019 | Karachhuliya Grant | 111 | 95 | 86 | Work In Progress | Not Certified |
| 4 | Siddharth Nagar | Uska Bazar | Nagawa | 447020 | Nagawa | 285 | 265 | 93 | Work In Progress | Not Certified |