Scheme Details

S.No. District Name Agency Name Scheme Id Scheme Name Estimated Cost Expenditure Approve By Agency Status Approve By EE Status Automation Status
1 Siddharth Nagar JAKSON - VISHVARAJ (JV) 20101833 Tighari Ray GP WSS 225.23 57.21 Verified Verified Not Integrated

Scheme Assigne Villages

Sno. District Name Bolck Panchayat Village ID Village Name House Holds FHTC FHTC % Har Gar Jal Certified Handed Over Villages
1 Siddharth Nagar Khuniyaon Tighari Ray 448388 Tighari Rai 104 103 99 Work In Progress Not Certified Not Verified
2 Siddharth Nagar Khuniyaon Tighari Ray 448389 Mankhoriya Kot 45 5 11 Work In Progress Not Certified Not Verified
3 Siddharth Nagar Khuniyaon Tighari Ray 448390 Bangawa 37 30 81 Work In Progress Not Certified Not Verified

Scheme Progress

Village Covered T/W OHT Solar Plant Electric Distribution (Line Laying in meter.)
Required Boring Done Air Compressor done O. P. Unit done Required Work Started Work Completed Required Procured (KW) Work status Required Transformer Procured Work status Total Length Length Laid
3 1 1 1 1 1 0 0 13 0 NA 0 NA No 7449.00 7400.00