Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Deoria | Gayatri Projects LTD | 8359018 | Basantpur P water supply scheme | 151.76 | 149.12 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 2 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 26 | 25 | Yes | 0 | NA | No | 8766.77 | 7895.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Deoria | Desai Deoria | Basantpur. | 459215 | Nibi Barwa | 100 | 99 | 99 | Work In Progress | Not Certified |
| 2 | Deoria | Desai Deoria | Basantpur. | 459216 | Basantpur | 285 | 285 | 100 | Har Gar Jal | Not Certified |