Jal Jeevan Mission-Agency Dashboard

Heirarchy Details
Assign District:
Assign Scheme :
Assign Villages :
Physical Progress
Households :
FHTC :
FHTC(%) :
Total HGJ :
Total Certified :
HO Villages :
Incoming Complaints Received
All Complaints :
Close Complaints :
Pending Complaints :
Feedback from Gram Pradhan On Call
All Complaints :
Close Complaints :
Pending Complaints :
Estimated Cost and Expenditure Detaile(In Lacs)
Estimated Cost :
Expenditure :
Expenditure(%) :
Agency Progress Details
Sr.No. District No Of Scheme No Of Village households FHTC FHTC % Har Gar Gal Certified
1 2 3 4 5 6 7 8 9
1 Etawah 94 159 45516 44123 96.94% 90 48
Components Wise Physical Progress
Sr.No. Components Taget Achivement %
1 2 3 4 5
1 Tubewell 100 99 99.00
2 Pump House 100 93 93.00
3 Chlorination system 50 47 94.00
4 OHT 98 98/93 100.00
5 Distribution (Line Laying in Km.) 889 811 91.23
6 Solar Plant 94 83 88.30
7 F.H.T.C. 45516 44123 96.94
8 W.T.P. 0 0 0.00
9 ROAD DISMENTLING/RESTORATION(KM) 256 252 98.44
10 Villages where 100 % road restoration completed 97064 59993 61.81
11 Comissioning of Village 159 123 77.36
12 Regular water supply 159 121 76.10