Sr.No. District Town Name of Sewerage Project Scheeme Type Mode of Project AA&ES and date No. of STP STP Capacity No.Of Drains Agency Name Agreement Cost
Date of Start
Date of Comp. As per Agreement
Revised Date
Current progress
Date of updation
Remark
Date of Sanction Sanction cost (In Cr.) work Cost (In Cr.) Centage (In Cr.) O & M Cost (In Cr.) Physical Progress Financial Progress
Total -- 6166.90 3075.35 210.09 2719.49 38 1149.10 194 -- 3696.97 -- -- --
--
+ 42.06
1369.87
-- --
1 Agra Agra Agra Sewerage Scheme( Interception & diversion and STP works) NGP2-EAP HAM 06-May-2020 842.25 371.29 25.40 445.56 13 177.60 26 M/s AWWMPL Pvt Ltd 582.84 05-Apr-2023 04-Apr-2025 04-Apr-2025,
31-Dec-2025,
31-Dec-2026
+0.01
88.99
+0.00
336.24
14-Sep-2026
  • Component wise progress of Agra (HAM) 100 MLD STP- 68%, WIP 35 MLD STP- 76.2, WIP 31 MLD STP- 76.48%, WIP MPS 03 Nos.- 73%, WIP Rising Main 9.55 Km- 55%%, WIP Gravity Sewer 2.55 Km- 80%, WIP DSTP 10 Nos.- 5%, WIP Note- 1st Stage permission is granted for 07 Nos. DSTP Forest Land and 2nd stage permission is under process
  • As per pervious meeting discussion, In order to complete the remaining works of 31 MLD and 35 MLD STP and make them operational as per the prescribed timeline, Direction has been given to firm to complete the works as early as possible by increasing manpower.
  • As per pervious meeting discussion, In order to 07 Nos. DSTP forest clearance , Land Gazette notification meeting has been conducted on 02.05.2025 and soon gazette notification will be published and after that stage 2 permission will be applied
  • 07 Nos. DSTP forest land clearance was granted by Forest Department in September 2025, after that work is going on and current physical progress of DSTP Package is 34.50%
2 Agra Balance Darins Tapping and Augmentation of SPSs at Agra City NGP DBOT 11-Jun-2025 126.41 86.37 6.90 34.01 0 0.00 0 66.86 02-Apr-2026 01-Oct-2027 +0.00
0.00
+0.00
0.00
21-Apr-2026
3 Bulandshahr Gulaothi I&D works NMCG DBOT 28-Aug-2024 50.98 20.86 1.37 24.69 1 10.00 1 M/s SKC Technocrat Pvt. Ltd (Formerly M/s Satish Kumar & Co.) & M/s Malvika Technical Services (JV) 51.19 01-Dec-2025 31-May-2027 +0.00
12.00
+0.00
2.09
31-Aug-2026
  • Approved BEP and Drawing & Design of Boundary wall submitted. Construction work of Boundary Wall is in progess.
  • Physical Progress is less as per agreement norms. A show cause letter has been issued to firm on Dt. 30.06.2026
  • Soil Testing Complete. Boundary Wall work is in progress.
  • AA&ES issued on Dt 28.08.2024
  • NIT issued by SE, Meerut vide letter no. 257/731/15 Dt 08.11.2024
  • LOA & Date of start is given on 26.11.2025. Date of start is 01.12.2025 & Date of completion of work is 31.05.2027 issued to M/s SKC Technocrat Private Limited- M/s Malvika Technical Services (JV), B-29, RDC, Raj Nagar, Ghaziabad- 201002
  • The land purchase proposal has been Sanctioned and GO issued. The funds Released to ULB Gulaothi. Land Registry work is completed. ULB handed over the land to U.P. Jal Nigam for work on Dated 20.12.2025.
  • Mobilization Amount of Rs. 1.04 Crore claimed by firm.
  • Revised BEP submitted by the firm. BEP send to IIT BHU for vetting After checking it.
  • 2nd Mobilization Amount of Rs. 1.04 Crore claimed by firm.
  • BEP submitted by the firm on Dated 03.02.2026. Some Observation were found in the examination of BEP, after which BEP was returned to the firm on 08.02.2026.
4 Chandauli I&D and STP works at Pt Deen Dayal Upadhyay Nagar Chandauli NGP2-NON EAP HAM 22-Jan-2025 262.78 95.00 7.60 129.67 1 45.00 2 0.00 +0.00
0.00
+0.00
0.00
22-Aug-2026
  • NMCG has approved the letter send by the UPJN,waiving the APS imposed on the firm.
  • Letter written to NMCG on 19.05.2026 to take decision about the APS imposed
  • Guidance received from NMCG on 26.06.2026 regarding APS
  • Pre-bid meeting held on 09.07.2025
  • Bids will be opened on 19.08.2025
  • Draft Pre-bid reply sent to CE(Ganga) on 04.08.2025
  • Pre-bid reply sent to NMCG for approval on 14.08.2025 after approval from CE(Ganga) and SMCG
  • Date for bid opening extended upto 04.09.2025
  • Date of bid opening is 07.10.2025
  • AAE&S issued on 22.01.2025
  • Revised model RFP Document received from NMCG on 06.05.2025, RFP sent to NMCG on 23.05.2025 for approval
  • Approved RFP Documents received from NMCG on 18.06.2025. NIT Shall be issued on 21.06.2025
  • NIT issued on 21.06.2025. Tender also published on e-Tender portal on 24.06.2025
  • Bids opened on 07.10.2025. Technical evaluation in process
  • Financial bids opened on 07.01.2026. CBER sent to NMCG on 03.02.2026 for approval
  • Approval of CBER received from NMCG on 20.02.2026 and communicated by CE(Ganga) on 23.02.2026
  • M/s Enviro Infra Engineers Limited has been selected as L1 bidder
  • LOA issued on 25.02.2026
  • Bidder has accepted the LOA and has given undertaking regarding the APS
  • SPV has been formed and draft Concession Agreement shall be shared with NMCG by 30.07.2026
  • Bidder vide its letter 03.03.3036 has requested to waive off the APS imposed for which guidance has been sought from HQ
  • M/s Enviro Infra Engineers Limited has been informed regarding waiving off the APS imposed and instructed to accept the LOA and sign the Concession Agreement
  • CA signed on 20.08.2026
5 Hapur Hapur I&D and STP works at District-Hapur NGP DBOT 19-Sep-2023 49.06 22.85 1.42 24.79 1 6.00 1 M/s SKC Technocrat Pvt. Ltd (Formerly M/s Satish Kumar & Co.) & M/s. Geo Miller & Co. Pvt. Ltd. (JV) 39.28 08-Nov-2024 07-Feb-2026 31-Oct-2026 +0.00
68.00
+0.00
9.17
14-Sep-2026
  • Revised vetted BEP Civil/Mechanical GA & R/F of MPS, SHU and SBR has been submitted by the firm on Dt 25.10.2025 and approved by the Department except Civil GA and R/F of SBR.
  • Date of start is given on 08.11.24. Date of completion of work is 05.02.2026 to M/s SKC Technocrat Pvt. Ltd (Formerly M/s Satish Kumar & Co.) & M/s. Geo Miller & Co. Pvt. Ltd. (JV), Reg. Office B-29, IIIrd Floor, RDC Rajnagar, Ghaziabad - 201013. AGREEMENT cost of project is Rs. 39,28,13,617.00.
  • Land Issue Resolved in March 2025.
  • The amount of mobilization advance has been claimed by the firm.
  • BEP and GAD sent for vetting to IIT BHU VARANASI on 19.06.25
  • SBR Civil work Completed, MPS & STP work is in progress.
  • LD of Rs. 65.00 Lac has been imposed on firm for delay of work, as per contract agreement.
6 Hathras Hathras I&D and STP works at Hathras Town NGP DBOT 30-Jan-2023 128.91 70.48 4.55 53.88 1 24.00 10 M/s Neercare India pvt KLtd JV M/s EMIT Group India Pvt Ltd JV EMS Ltd 119.05 06-Sep-2024 05-Jun-2026 30-Nov-2026,
31-Dec-2026
+0.05
67.55
+0.00
20.69
14-Sep-2026
  • Project was delayed as the land for STP was handed over in March 2025 by Nagar Palika Parishad Hathras. After that Design drawing has been vetted by IIT and work is carried on and current physical progress of the project is 63.50%
  • Date of start is 06.09.2024 and date of completion is 05.06.2024. Survey work is going on.
  • Survey and soil investigation has been completed by firm
  • Project was delayed as the land for STP was handed over in March 2025 by Nagar Palika Parishad Hathras. After that BEP is approved and structural drawings of SBR also vetted by IIT and at present excavation for SBR is in progress
7 Kanpur Nagar Interception & Diversion Of 14 Untapped Drains Of Kanpur City (Along with Supplementary Works) NGP2-NON EAP DBOT 02-May-2025 138.11 97.17 7.77 2.03 0 0.00 14 M/s Technocraft Ventures Limited 79.39 09-Jan-2026 08-Jul-2027 +0.00
11.70
+0.00
0.00
14-Sep-2026
8 Lucknow Pollution Abatement Of Gomti River (Phase 1 Part 1) Lucknow NGP DBOT 29-Jul-2024 240.93 123.45 6.97 110.51 2 42.50 2 M/s R.K. Engineers- Khilari Infrastructure (JV) 187.90 07-Sep-2024 06-Jun-2026 31-Jan-2027 +0.66
95.91
+0.00
129.69
14-Sep-2026
  • 39 MLD STP Daulatganj Operation & Maintenance started on dt. 05.11.2024.
  • SBR Basin - Blower piping work completed. CCT - Hydro testing work completed. MPS - All RCC work completed. PTU -All RCC work completed. HT Building - Plaster work completed and painting work in progress. Admin Building - Inner side plaster work completed and flooring, outer side plaster & painting work is in progress. SHU - Terrace slab completed and brick work with paster work is in progress. 8. Transformer yard & DG Platform- Casting work is completed. I&D - Incoming sewer pipe supply completed. Supply of Decanter & Defuser completed. Supply of PLC Panel, Motor of MPS, RAS, SAS Pump & Blower completed. Air blower piping work completed.
9 Lucknow Lucknow Pollution Abatement of Gomti River (Phase-II, Part-I) Lucknow NGP DBOT 30-Jan-2023 264.67 137.55 8.53 118.60 1 50.00 3 M/s R.K. Engineers- Khilari Infrastructure (JV) 187.74 14-Jun-2024 13-Mar-2026 04-Jun-2027 +0.01
26.07
+0.00
24.12
14-Sep-2026
  • Design & Drawing work is in progress. SBR Basin 4 - Wall casting upto 3rd lift completed. SBR Basin 3- Wall 5th lift work is in progress. SBR Basin 2 -Decanter wall and common wall 4th lift work is in progress. IPS - Wall 5th lift casting completed. Approach Sewer- Laying work is in progress. Work stop due to site water logging. De-watering work is in progress.
10 Lucknow Lucknow Pollution Abatement of Gomti River (Phase-II, Part-II ) Lucknow NGP HAM 19-Sep-2023 351.03 207.99 13.14 129.90 0 0.00 1 M/s TEPL Lucknow Wastewater Management Pvt. Ltd. 202.64 23-Jun-2026 22-Jun-2028 +2.00
15.44
+0.00
0.00
15-Sep-2026
  • Date of Start given to firm M/s TEPL Lucknow Waste Water Management Pvt. Ltd. on 23.06.2026
  • Design & Drawing work is in progress. 828 cum out of 2731cum completed. concrete at basins 4 & 3. Reinforcement Work in Progress at basin 2, 3, 5&6. 18 nos Columns concrete completed. upto 1st slab of staff quarter. Column concrete work complete upto 1st lift above plinth beam for admin building.
  • Concessionaire Agreement has been signed on dt. 26.08.2025.
11 Mathura Chhata Chhata Town Sewerage Scheme (I&D and STP works), District Mathura NGP DBOT 25-Oct-2022 56.15 34.52 2.23 19.40 1 6.00 14 M/s Shailesh Kumar J.V. 48.97 12-Nov-2024 11-Aug-2026 30-Sep-2027 +0.90
24.00
+0.00
2.69
14-Sep-2026
  • STP site is flooded due to overflow from Bahrauli branch drain, (situated near to the site) from 1 month. The current water level at STP site is higher to the HFL, provided by irrigation department. At this situation all works are heavily affected. Not only in present this kind of situation during monsoon will affect the operation and maintenance services in later too. Due to the current scenario of site, we have sent a letter to SDM, Chhata, requesting a new land for construction of STP in this project with all requisite details of the scenario of original project site.
  • Date of Start 12.11.2024 has been given to the firm.
  • Survey and soil investigation has completed by firm.
  • BEP of STP has been approved.
  • Boundary wall construction work is going on at site.
  • Project is slightly delayed due to problem of water logging at STP Site as PWD, Mathura was constructing a culvert on Kosi Drain and due to diversion of drain the water of kosi drain got obstructed. The STP site is located near to the branch drain of kosi drain at upstream side which got over flowed and leading to water logging at STP Site.This hindrance cleared in march 2025 after that work was resumed.
  • Construction of HTS and staff quarter building is in progress at MPS.
12 Mathura Vrindavan I&D and 13 MLD STP works at Vrindavan City NGP DBOT 25-Oct-2022 77.70 39.90 2.56 35.24 1 13.00 2 M/s SIMA -G D- N.P. (JV) 65.86 11-Jun-2024 10-Mar-2026 31-Oct-2026 +0.00
95.66
+0.00
35.24
14-Sep-2026
  • STP site had been water logged from 10.08.2025 to 18.09.2025, due to the high flood of Yamuna. After receding of water construction work is in progress along with corrective works due to the damage by flood at site.
  • Kalideh MPS rising main works has been done.
  • STP site is water logged from 10.08.2025, work is affected due to this
  • LOA issued to firm on dated 15.03.2024. Effective Date of start for the work is 11.06.2024.Work is in progress.
  • Work is going in SBR basin, CCT, Admin building, Pannel room, SHU and in MPS units.
  • 13 MLD STP has been taken under trial run from dt 25-03-2026, balance work is ongoing,whic is expected to be completed in july 2026.
  • The STP is under trial & run from 25-03-2026, alongwith balance associated works are ongoing.
13 Mathura Kosi Kalan I&D and STP works at Kosi Kalan Town, District Mathura NGP DBOT 25-Oct-2022 66.59 31.24 2.03 33.32 1 12.00 1 M/s R K Engineers Sales Ltd 53.60 16-Oct-2024 15-Jul-2026 31-Dec-2026 +0.61
55.66
+0.00
13.52
14-Sep-2026
  • Survey and soil investigation has been done by firm.
  • Ground improvement work of SBR basin is completed, PCC work is in progress.
  • LOA has been issued on date 18.06.2024 and Date of start has been given 16.10.2024 to the firm. Survey work is going on
  • Continous instruction has been given to firm for expediting the work.
  • BEP of STP has been approved.
  • Boundary wall construction work is going on at site.
  • Preparation for PCC work of SBR basin is in progress, hindered due to rain at site.
14 Mathura Mathura Mathura sewerage scheme (I&D and STP Works for balance drain) NGP2-NON EAP HAM 07-Sep-2022 292.56 149.85 9.61 133.10 1 60.00 4 M/s EIEL Mathura Infra Engineers Private Limited 240.01 30-Nov-2024 29-Nov-2026 +0.10
97.10
+0.00
155.37
14-Sep-2026
  • Effective date of start has been given to concessionaire as 30.11.2024.
  • IPS Kala Patthar civil work and its Rising main has been completed
  • SBR basin and MPS construction work is in progress in STP premises.
  • Dairy farm IPS rising main laying work is in progress.
  • LOA issued to L1 Bidder on on 27.09.2023. CA signed on 12.12.2023. Effective date of start shall be to concessionaire after financial closure.
15 Meerut Meerut I&D and STP works at Meerut NGP2-EAP HAM 06-May-2020 690.71 363.78 26.31 280.19 1 220.00 2 M/s. Meerut STP Pvt. Ltd. 369.74 11-Nov-2024 10-Nov-2026 +1.29
66.84
+0.00
191.82
14-Sep-2026
  • ESIA/ ESMP under review with World Bank
  • BEP of EPS and Pipeline works has been recommended by PE.
  • . Payment for1st and 2nd MS have been released
  • BEP, Layout and HFD approved for 220 MLD STP, 2 I&D’s & MPS, BEP of Treated Effluent Pipeline from Lohia Nagar STP to Outfall pending with Concessionaire, BEP of EPS and Pipeline pending with Concessionaire. GAD, Structural Design and Dwg. for Admin Building, SBR, CCT, Tonner Room approved QAP, Date Sheet and GAD of Decanter, Diffuser approved, QAP, Date Sheet and GAD of Air Blowers under review., Vortex Grit Remover approved by PE. GAD of Primary Clarifier approved by UPJN. , QAP, Date Sheet and GAD of Chlorination System pending with Concessionaire. QAP of Filter Belt Press pending with Concessionaire., Revised QAP of Pumps to be submitted by Concessionaire. Revised GAD of MPS pending with Concessionaire.
  • Work in progress at only 1 front of STP, Concessionaire need to open multiple working fronts. Inadequate Manpower deployment at site, Manpower deployment to be increased.
  • QAP, Date Sheet and GAD of Decanter, Diffuser, Vortex Grit Chamber, Turbo Air Blower, Fine & Coarse Screens, Chlorination System & Leak Absorption System, RAS SAS, RSTP Pumps, Belt Filter Press, Gravity Belt Thickener, Screw Pumps approved.
  • QAP, Date Sheet and GAD of Gas Flare System, under re-submission., RCC drawing & design Calculations of Odean Nala I&D under re-submission.
  • GAD, Blower & Panel Building, SBR piping, HT panel & workshop, Security HT Panel-2 Metering Room, Electrical BEP, pending with Concessionaire. GAD of Odean Nala & Abu Nala-2 I&Ds under review with IIT Roorkee., RCC of Compound walls approved.
16 Pratapgarh Faecal Sludge Management for Pollution abatement of river Ganga at Manikpur, Pratapgarh Non EAP DBOT 22-Jan-2025 8.56 5.73 0.19 1.90 0 0.00 0 M/s Aastha Enviro Engineers Pvt Ltd 4.62 05-Feb-2026 04-Nov-2026 +0.00
38.00
+0.00
0.00
14-Sep-2026
  • Foundation work is under progress for various unit.
  • Vetting of BEP, Design & Drawing is completed.
  • Construction of staff quarter, admin building cum lab are under progress.
  • NMCG New Delhi has given approval for issuance of LOA to the L1 Firm M/s Aastha
  • LOA has been issued to firm on dated 23.12.2025
  • Date of start has been issued to firm on dated 04.02.2026. Date of start 05.02.2026 and Date of Completion 04.11.2026
  • Soil test has been done, Survey and site cleaning work is under progress.
  • Construction of Boundary wall is under progress.
17 PrayagRaj Prayagraj Interception, Diversion of Balance 13 drains and Augmentation of Salori STP capacity by 43 MLD (Sewerage District-C) at Prayagraj Uttar Pradesh under DBOT mode NGP DBOT 14-Mar-2023 331.75 180.27 11.22 140.27 1 43.00 13 M/s HNB Private ltd. - M/s Tirupati Cements Products (JV) 204.40 19-Mar-2024 18-Aug-2025 +0.00
97.89
+0.00
99.95
14-Sep-2026
  • 4070 m laying of Rising main completed.
  • Sitaram Ghat SPS- RCC work for wet well is under progress.
  • Gravity intercepter line has been completed. Manhole work is under progress.
  • RCC work for 6 nos I&D iscompleted. Balance work is under progress.
  • 43 MLD Salori STP is under partial trial run since dated 31.12.2025.
  • RCC work for PTU, SBR Basin, CCT Unit, MCC Room ,Chlorination room, chlorine tonner yard, Air Blower room, Sludge Dewatering Unit & TEPS is completed.
  • Drainage , Campus Road and landscaping work is under progress with in STP Campus.
  • Approach road work is under progress.
  • RCC work completed for Admin Building and Staff quarter, Finishing work is under progress.
  • Casting of 11th Lift of Wall at AB Culvert SPS has been completed. Staff quarter, Compound wall & other balance work is under progress.
  • BEP, Design & drawing has been approved by UPN (R) and same has been vetted by IIT Delhi.
18 PrayagRaj Prayagraj Interception, Diversion of Balance 7 drains and Augmentation of Rajapur STP capacity by 90 MLD (Sewerage District-D) at Prayagraj Uttar Pradesh under DBOT mode NGP DBOT 27-Jan-2023 475.98 242.85 15.24 217.89 1 90.00 7 M/s Triveni Engineering and Industries 309.74 24-Aug-2024 23-Feb-2026 +0.01
87.71
+0.00
115.29
14-Sep-2026
  • RCC work of TEPH is completed. Mechanical work is in progress.
  • RCC work of workshop Building,sub station Building is completed, Finishing work is under progress.
  • RCC work for Air Blower Building is completed . Finishing work is under progress.
  • Admin Building & BFP building - RCC work is under Progress.
  • RCC and well sinking work is under progress for Rajapur 56 mld MPS.
  • RCC work is under progress for Mumfordganj 39 mld MPS.
  • Shifting of Existing Rising main inside Mumfordganj SPS Campus work is completed.
  • 3150 m laying of Rising main completed. Balance Laying is under progress.
  • 1510 m laying of Gravity main (Sadar Bazar) & 2409 m laying of Gravity main (Sankar Ghat) completed Balance Laying is under progress.
  • RCC work completed for 6 Nos I&D. Mechanical work is under progress.
  • Plinth Beam Casting is Completed for PTU, Column Casting is under Progress.
  • RCC work & Hydro test of SBR Basin 1,3& 4 is completed.
  • Walkway & channel work is under progress
  • RCC work & Hydro test of CCT is completed.
19 PrayagRaj Prayagraj Interception, Diversion of Balance discharge of 02 drains and 50 MLD STP to Augment existing Treatment Capacity (80 MLD) Naini STP for Sewerage District-A at Prayagraj Uttar Pradesh under DBOT mode NGP DBOT 05-Sep-2023 186.47 83.71 5.44 97.32 1 50.00 2 M/s JWIL-SSG (Joint Venture) 95.57 04-Mar-2025 03-Jul-2026 +1.76
79.07
+0.00
38.94
14-Sep-2026
  • Gravel padding, PCC and Reinforcement of CCT raft Wall & Walkway is completed.
  • Excavation, Reinforcement and Concreting work upto slab level is completed in PTU Walkway work is completed.
  • Piling work of I&D Structure is completed.
  • Concreting work of Grid Slab of SBR basin-1, 2 3 &4 is completed and shuttering, reinforcement and concreting work of basin wall - 1 2 3 & 4 upto 100% height is completed. Walkway work also completed .
  • Excavation, PCC of work shop building is completed Column work is under progress.
  • Soil testing of STP & SPS site has been completed.
  • BEP and Structure design and drawing has been Approved for 2.90 MLD Bargad Ghat SPS
  • Wet Well of SPS is completed.
  • Casting of columns of claritubesettler is completed and shuttering work of beam and grade slab iscompleted.
  • Staff quarter Bricks works in progress.
  • Gravel padding, PCC and raft of Admin Building is completed and reinforcement & shuttering work of plinth beam is completed.
  • Finishing work of Security Cabin is completed.
  • Workshop Building Bricks works is in progress.
  • Dewatering Building foundation completed Column work is also completed.
  • Decenter Blower clorination system Gate Screen, Screw Press Screen and diffuser is receieved at site.
  • Approach bridge Pilling work completed.
  • Gates and screen installation work in PTU is completed
  • Gas engine Building Foundation work completed.
  • Decenter installation is in progress.
  • Raising MainPipeline work in progress
20 Rae Bareli DPR OF 08 KLD Fecal Sludge Treatment Plant At Dalmau Raibareli NMCG DBOT 28-Aug-2024 4.40 3.01 0.18 1.21 0 0.00 9 M/s Aastha Enviro Engineers Pvt Ltd 3.00 06-Feb-2026 05-Nov-2026 +0.00
19.15
+0.00
0.00
14-Sep-2026
  • Date of start given to Firm M/s Aastha Enviro Engineers Pvt. Ltd. on dt. 06.02.2026.
  • Bid Document uploaded at e-tender portal on dt. 27.06.2025.
  • Pre-bid Meeting dt. 04.07.2025 at 12:00 PM.
  • Technical Bid open on dt. 22.08.2025.
  • TBER sent to NMCG for review and approval.
  • NOC received from NMCG on dt. 03.10.2025.
  • LOA issued to Firm M/s Aastha Enviro Engineers Pvt. Ltd. on dt. 30.12.2025.
  • Pre-bid reply sent to NMCG for review and approval on dt. 07.07.2025.
  • NMCG sent final pre-bid replies on dt. 05.08.2025.
  • Soil testing and Survey completed. Design & Drawing work is in progress. Boundary wall plaster work is in progress. Staff quarter & lab, Admin building-Shuttering work is in progress.
  • Final pre-bid replies uploaded on e-tender portal on dt. 07.08.2025 Bid Submission date 22.08.2025.
  • Financial bid open on dt. 10.10.2025. Financial Evaluation work is in progress.
  • FBER sent to NMCG for review and approval on dt. 01.12.2025.
  • NOC received from NMCG of FBER on dt. 19.12.2025
21 Saharanpur I&D and STP Work in Deobandh NGP DBOT 25-Jul-2024 134.71 67.42 4.46 62.83 1 20.00 4 M/s 21st Century Enviro Engineers Pvt. Ltd. -M/s Sattva Engineering Const. Ltd. JV 95.25 09-Feb-2026 08-Jul-2027 +0.00
0.00
+0.00
0.00
14-Sep-2026
  • Construction activity has been stopped in compliance with the directions issued by the Superintending Engineer, Circle Office, Uttar Pradesh Jal Nigam (Rural), Saharanpur, vide letter no. 168/122 (Namami Gange)/44 dated 20.02.2026, due to an increase in drain discharge from 13.8 MLD to 20.36 MLD, with instructions to the firm not to commence construction activities.
  • Letter to lowest bidder regarding power consumption written on dated 14.08.2025 last date for reply is 20.08.2025
  • Reply received on dated 20.08.2025
  • LOA issued to M/s 21st Century Enviro Engineers Pvt. Ltd. -M/s Sattva Engineering Const. Ltd. JV. on dt. 14.11.2025
  • Financial bid send to NMCG on dated 04.09.2025
  • Approval recieved on 16.09.2025
  • AA&ES recieved on 25.07.2024.
  • NOC on pre- Bid Documents recieved 0n 18.12.2024
  • Technical Bid opened on 25.01.2025
  • Technical bid evaluation sheet and document send to NMCG on 28.04.2025
  • Approval on Technical bid from NMCG recieved on 29.07.2025
  • Pre-bid meeting held on 07.11.2024
  • Financial bid opened on 07-08-2025 and financial evaluation under process.
  • Draft bid document and NIT sent to NMCG on 05.08.2024 for approval.
  • Comments on draft Bid Documents recieved on 17.10.2024
  • NIT published on 24-10-2024
  • Draft pre-bid reply send to NMCG 24.11.2024
22 Saharanpur Saharanpur I&D and STP works at Saharanpur NGP2-EAP HAM 16-Jun-2022 577.23 266.34 20.55 290.34 1 135.00 61 M/s Enviro Infra Engineers Ltd, Bhugan Infracon Pvt. Ltd. & Micro Transmission System, JV 343.88 01-Nov-2025 31-Oct-2027 +1.16
40.70
+42.06
115.81
14-Sep-2026
  • In the review meeting on 25.04.25 at NMCG, UPJN-R/PE were asked to work out on the possible alternatives options like retaining wall option, backfilling option or others etc. Post which UPJN-R and PE had to work on optimization of the solution and comeback with all possible solution. Accordingly, additional cost implication worth Rs. 81 crore for STP due to level difference sent to NMCG on 21.04.25
  • Out of various feasible technical solutions to counter the implication arose due to mis-match of site data, option no. 4 has been approved in-principle by NMCG and communicated vide letter no. Pr-13011/1/2022 – O/o PS NMCG dated 03.10.2025. Concessionaire have to submit the detailed estimate with in one month.
  • Effective date of start 01.11.2025 given to concessionaire vide Lt. 1077/122(Namami Gange)132 dt. 31.10.2025
  • LOA issue on dt. 26.07.2024. CA signed on dated 27.09.2024. Financial Closure documents submitted in NMCG, is under scrutiny.
  • About 6.0 m level differnces as given in tender document and actual site level. as discussed NMCG meeting held on 07.01.2025.
23 Sant Ravidas Nagar Bhadohi Interception and Diversion of Drains/Nala Falling in Varuna River and STP for Bhadohi Town NGP2-NON EAP DBOT 06-Mar-2025 127.26 52.86 4.23 54.69 3 25.00 4 M/s VVIP Infratech Ltd., Ghaziabad 80.97 01-Jul-2026 31-Mar-2028 +0.00
1.00
+0.00
0.00
11-Aug-2026
  • Date of start id 01.07.2026 and Date of completion is 31.03.2028
  • Bids opened on 09.10.2025. technical evaluation in process
  • Financial bids opened on 05.01.2026. CBER sent to NMCG on 03.02.2026 for approval
  • LOA issued on 12.05.2026
  • Agreement signed on 19.06.2026
  • Date of start is 01.07.2026
  • AAE&S issued on 06.03.2025
  • draft Tender Documents sent to NMCG for approval on 10.06.2025. Approval awaited
  • Comments on draft documents are received from NMCG to which compliance shall be sent by 17.07.2025
  • NIT issued on 31.07.2025
  • Bids will be opened on 10.09.2025
  • Pre Bid meeting scheduled on 18.08.2025
  • Pre-bid meeting held on 18.08.2025. Reply to queries shall be sent by 24.08.2025
  • Reply to query sent to CE(Ganga) on 24.08.2025 and after discussion sent to NMCG on 01.09.2025
  • Bids will be opened on 09.10.2025
24 Shamli Banat I&D and STP Work in Banat, Shamli NGP DBOT 25-May-2023 48.71 24.93 1.58 22.20 1 5.00 3 M/s R K Engineers Sales Ltd 37.92 14-Oct-2024 13-Apr-2026 31-Dec-2026 +0.20
75.05
+0.00
14.70
14-Sep-2026
  • Contract Agreement is signed on 08.10.2024 and Date of Start 14-10-2024 & Date of Completion 13-01-2026
  • Survey and Soil investigation work completed
  • BEP, Layout and HFD approved for 05 MLD STP.
  • GAD, Structural Design and Dwg. for SBR and Boundary wall approved.
  • Approach Road and boundary wall work in progress
  • GAD for Sludge Handling Unit Submitted, which are clear for Vetting & Structural Design.
  • Project is 4 months behind schedule.
  • Delay in design/drawing submission by Contractor.
  • Contractor need to increase expedite the progress of work and submission of design/drawings.
  • GAD, Structural Design and Dwg. for SHU approved
  • GAD, Structural design and drawing of I&D Structure approved
  • GAD and Data Sheet of Diffuser and decanter approved
  • BEP, P&ID of MPS approved
  • GAD, Structural design and drawing of PTU Structure approved
  • GAD, Structural design and drawing of CCT, HT Substation Building and MPS which are clear for Vetting.
  • Structural Design and Dwg. for MPS approved
  • Data Sheet, QAP, Curves etc. of Turbo Blower, Centrifuge approved
  • Gate Schedule approved
  • GAD, Structural design and drawing of CCT with Tonner Room & HT Substation approved
25 Shamli Bantikhera Banat I&D and STP Work in Bantikhera and Babri village, Shamli NGP DBOT 25-May-2023 55.47 29.41 1.84 24.22 1 5.00 1 M/s R K Engineers Sales Ltd 41.91 14-Oct-2024 13-Apr-2026 30-Jun-2026,
30-Jun-2027
+2.40
19.60
+0.00
3.62
14-Sep-2026
  • Date Sheet, QAP, Curves etc. of Turbo Blower, Centrifuge approved
  • Contract Agreement is signed on 08.10.2024 and Date of Start 14-10-2024 & Date of Completion 13-01-2026
  • Survey and Soil investigation work completed
  • BEP, Layout and HFD approved for 05 MLD STP.
  • Work halted due to unresolved land dispute.
  • Project is 7 months behind schedule.
  • GAD of SBR is Clear for Vetting and Structural design
  • Gate Schedule approved
  • GAD, Structural design & Dwg. of PTU approved
26 Shamli Shamli I&D and STP Work in Shamli NGP DBOT 25-May-2023 206.02 103.19 6.66 96.17 1 40.00 1 M/s R.K. Engineers Sales Ltd.-M/s Anand Constrwell Pvt. Ldt. (JV) 120.92 14-Oct-2024 13-Apr-2026 31-Dec-2026 +0.20
79.55
+0.00
41.81
14-Sep-2026
  • GAD, Structural Design and Dwg. for SBR and Boundary wall approved.
  • GAD for Admin Building and Sludge Handling and Dewatering Building Submitted, which clear for Vetting & Structural Design.
  • CCT and I&D GAD Submitted, which clear for Vetting & Structural Design.
  • Project is 4 months behind schedule.
  • Delay in design/drawing submission by Contractor.
  • Contractor need to increase expedite the progress of work and submission of design/drawings.
  • GAD, Structural Design and Dwg. for SHU approved
  • GAD, Structural Design and Dwg. of I&D Structure approved
  • GAD and Data sheet of Decanter and diffuser approved
  • GAD, Structural Design and Dwg. for Admin. Building & Lab approved
  • GAD, Structural Design and Dwg. of Staff Quarter approved
  • Gate Schedule & Electrical load list approved
  • GAD, Structural Design and Dwg. of CCT/Toner Room & Fiber Disk Filter approved
  • GAD, Structural Design and Dwg. for MPS approved
  • Contract Agreement is signed on 08.10.2024 and Date of Start 14-10-2024 & Date of Completion 13-01-2026
  • Approach Road and Boundary wall work in progress
  • BEP, Layout and HFD approved for 40 MLD STP.
  • Primary Clariflocculator GAD Submitted, which clear for Vetting & Structural Design.
  • CCT GAD Submitted which clear for Vetting & Structural Design.
  • BEP, P&ID, HFD of MPS approved
  • Data Sheet, QAP, Curves etc. of Turbo Blower, Centrifuge approved
27 Shamli Thanabhawan I&D and STP Work in Thanabhawan, Shamli NGP DBOT 25-May-2023 97.19 55.63 3.50 38.06 1 10.00 5 M/s R K Engineers Sales Ltd 63.72 14-Oct-2024 13-Apr-2026 31-Dec-2026 +0.20
70.00
+0.00
19.11
14-Sep-2026
  • GAD, Structural Design and Dwg. for PTU and CCT Submitted which are clear for Vetting
  • Structural Design and Dwg. for MPS submitted which is clear for Vetting
  • GAD of Fiber Disk filter submitted which is clear for vetting
  • Data Sheet, QAP, Curves etc. of Turbo Blower, Centrifuge approved
  • Gate Schedule & Electrical load list approved
  • Structural Design and Dwg. of PTU, Fiber Disk Filter, I&D and Sewer Network approved
  • Structural Design and Dwg. for MPS approved
  • Structural Design and Dwg. for CCT with Tonner Room approved
  • Contract Agreement is signed on 08.10.2024 and Date of Start 14-10-2024 & Date of Completion 13-01-2026
  • Survey and Soil investigation work completed
  • Approach Road work in progress
  • BEP, Layout and HFD approved for 10 MLD STP.
  • GAD, Structural Design and Dwg. for SBR and Boundary wall approved.
  • GAD for Sludge Handling Unit Submitted, which are clear for Vetting & Structural Design.
  • CCT GAD were Submitted, which clear for Vetting & Structural Design.
  • Boundary Wall work in progress
  • Project is 4 months behind schedule.
  • Delay in design/drawing submission by Contractor.
  • Contractor need to increase expedite the progress of work and submission of design/drawings.
  • GAD of MPS submitted which is clear for vetting
  • GAD, Structural Design and Dwg. for SHU approved
  • GAD and Data Sheet of Diffuser and decanter approved
  • BEP, P&ID of MPS approved
28 Varanasi I&D and STP works for Durga Drain (Sewerage District-IV), Varanasi NGP2-NON EAP HAM 06-Mar-2025 274.31 107.70 8.61 97.50 1 60.00 1 0.00 +0.00
0.00
+0.00
0.00
22-Aug-2026
  • M/s Enviro Infra Engineers Limited has been selected as L1 bidder
  • AAE&S issued on 06.03.2025
  • Revised Draft RFP Document received from NMCG on 06.05.2025, RFP shall be sent to NMCG by 29.05.2025 for approval
  • Daft RFP documents were sent to NMCG on which comments were received on 18.06.2025. Compliance/clarifications sent on 19.06.2025
  • M/s Enviro Infra Engineers Limited has been informed regarding waiving off the APS imposed and instructed to accept the LOA and sign the Concession Agreement
  • Bidder has accepted the LOA and has given undertaking regarding the APS.
  • SPV has been formed and draft Concession Agreement shall be shared with NMCG by 30.07.2026
  • CA signed on 20.08.2026
  • Bids will be opened on 07.10.2025
  • Bid submission date extended upto 27.08.2025
  • Bid submission extended upto 12.09.2025
  • Pre bid meeting held on 15.07.2025
  • NMCG has approved the letter send by the UPJN,waiving the APS imposed on the firm.
  • RFP invited on 27.06.2025 and bids shall be opened on 12.08.2025
  • Bids opened on 07.10.2025. technical evaluation in process
  • Financial bids opened on 07.01.2026. CBER sent to NMCG on 03.02.2026 for approval
  • Approval of CBER received from NMCG on 18.02.2026 and communicated by CE(Ganga) on 20.02.2026
  • Pre-bid reply sent to NMCG on 18.08.2025 after discussion with CE(Ganga) and SMCG
  • Guidance received from NMCG on 26.06.2026 regarding APS
  • Final approved RFP documents received from NMCG on 23.06.2025. RFP shall be floated by 27.06.2025
  • Bidder vide its letter 03.03.3036 has requested to waive off the APS imposed for which guidance has been sought from HQ
  • Letter written to NMCG on 19.05.2026 to take decision about the APS imposed