S.No. | District | Agency | Scheme Id | Scheme Name | Phase | No.Of.Village | T/W Approved | T/W Completed | Total OHT | OHT Completed | Distribution Line Laying Approved(KM) | Distribution Line Laying Completed(KM) | Har Gar Jal Villages | HGJ Certified Villages | Handed Over Villages |
1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Total | 11 | 11 | 11 | 11 | 11 | 65.56 | 64.32 | 11 | 11 | 8 | |||||
1 | Bulandshahr | Power Mech Projects Ltd | 8388628 | Rijhaura | PHASE-2 | 1 | 1 | 1 | 1 | 1 | 7.20 | 7.20 | 1 | 1 | 2 |
2 | Bulandshahr | Power Mech Projects Ltd | 8388633 | Bhandauli | PHASE-2 | 1 | 1 | 1 | 1 | 1 | 4.80 | 4.91 | 1 | 1 | 0 |
3 | Bulandshahr | Welspun Kaveri Infraprojects JV | 20011659 | Nagla Alampur WSS | PHASE-2 | 1 | 1 | 1 | 1 | 1 | 4.82 | 4.19 | 1 | 1 | 2 |
4 | Bulandshahr | JMC - Lakshmi (JV) | 20012166 | Ronda WSS | PHASE-2 | 1 | 1 | 1 | 1 | 1 | 7.52 | 7.00 | 1 | 1 | 0 |
5 | Bulandshahr | Power Mech Projects Ltd | 20012393 | Alipur Gijhauri | PHASE-2 | 1 | 1 | 1 | 1 | 1 | 3.40 | 3.40 | 1 | 1 | 2 |
6 | Bulandshahr | Power Mech Projects Ltd | 20012395 | Khawazapur Mirpur | PHASE-2 | 1 | 1 | 1 | 1 | 1 | 11.06 | 11.00 | 1 | 1 | 2 |
7 | Bulandshahr | Power Mech Projects Ltd | 20012413 | Basendua | PHASE-2 | 1 | 1 | 1 | 1 | 1 | 3.33 | 3.33 | 1 | 1 | 0 |
8 | Bulandshahr | Power Mech Projects Ltd | 20014617 | Akhtyarpur | PHASE-2 | 1 | 1 | 1 | 1 | 1 | 7.53 | 7.53 | 1 | 1 | 0 |
9 | Bulandshahr | Welspun Kaveri Infraprojects JV | 20100393 | Jatvai WSS | PHASE-2 | 1 | 1 | 1 | 1 | 1 | 6.36 | 6.36 | 1 | 1 | 0 |
10 | Bulandshahr | Welspun Kaveri Infraprojects JV | 20100408 | Kisola WSS | PHASE-2 | 1 | 1 | 1 | 1 | 1 | 5.90 | 5.90 | 1 | 1 | 0 |
11 | Bulandshahr | Welspun Kaveri Infraprojects JV | 20100419 | Sinhali WSS | PHASE-2 | 1 | 1 | 1 | 1 | 1 | 3.64 | 3.50 | 1 | 1 | 0 |