S.No. | District | Agency | Scheme Id | Scheme Name | Phase | No.Of.Village | T/W Approved | T/W Completed | Total OHT | OHT Completed | Distribution Line Laying Approved(KM) | Distribution Line Laying Completed(KM) | Har Gar Jal Villages | HGJ Certified Villages | Handed Over Villages |
1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Total | 349 | 0 | 0 | 132 | 132 | 3191.09 | 3186.24 | 348 | 331 | 0 | |||||
1 | Mahoba | N.K. Gupta & K.B. Gupta Contractors | 8175353 | kabrai GOV | PHASE-1 | 38 | 0 | 0 | 13 | 13 | 349.51 | 349.35 | 37 | 35 | 0 |
2 | Mahoba | Larsen & Toubro Ltd | 8009844 | Shivhar GOV | PHASE-1 | 61 | 0 | 0 | 18 | 18 | 672.57 | 672.20 | 61 | 61 | 0 |
3 | Mahoba | JMC-JWIL (JV) | 8009841 | Salaiya Khalsa Nathupura GOV | PHASE-1 | 77 | 0 | 0 | 40 | 40 | 785.00 | 784.25 | 77 | 76 | 0 |
4 | Mahoba | JMC-JWIL (JV) | 8009837 | Lahchura Kashipura GOV | PHASE-1 | 78 | 0 | 0 | 32 | 32 | 601.08 | 599.17 | 78 | 78 | 0 |
5 | Mahoba | SLC-SMC (JV) | 8152383 | Dhawarra GOV | PHASE-1 | 95 | 0 | 0 | 29 | 29 | 782.93 | 781.27 | 95 | 81 | 0 |