S.No. | District | Agency | Scheme Id | Scheme Name | Phase | No.Of.Village | T/W Approved | T/W Completed | Total OHT | OHT Completed | Distribution Line Laying Approved(KM) | Distribution Line Laying Completed(KM) | Har Gar Jal Villages | HGJ Certified Villages | Handed Over Villages |
1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Total | 414 | 0 | 0 | 136 | 128 | 4510.90 | 4225.70 | 412 | 156 | 0 | |||||
1 | Chitrakoot | Larsen & Toubro Ltd | 8134589 | Silauta Mustkil GOV | PHASE-1 | 59 | 0 | 0 | 17 | 17 | 576.00 | 538.34 | 59 | 53 | 0 |
2 | Chitrakoot | Larsen & Toubro Ltd | 8134609 | Chandi Bangar GOV | PHASE-1 | 286 | 0 | 0 | 91 | 86 | 3052.00 | 2846.86 | 284 | 59 | 0 |
3 | Chitrakoot | GVPR | 8135453 | Raipura GOV | PHASE-1 | 69 | 0 | 0 | 28 | 25 | 882.90 | 840.50 | 69 | 44 | 0 |