S.No. | District | Agency | Scheme Id | Scheme Name | Phase | No.Of.Village | T/W Approved | T/W Completed | Total OHT | OHT Completed | Distribution Line Laying Approved(KM) | Distribution Line Laying Completed(KM) | Har Gar Jal Villages | HGJ Certified Villages | Handed Over Villages |
1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Total | 15 | 8 | 8 | 8 | 8 | 62.30 | 62.39 | 15 | 12 | 0 | |||||
1 | Basti | Megha | 8360518 | Bhitihra GP WSS | PHASE-2 | 1 | 1 | 1 | 1 | 1 | 7.74 | 6.98 | 1 | 1 | 0 |
2 | Basti | Megha | 8360523 | Bhelwal GP WSS | PHASE-2 | 1 | 1 | 1 | 1 | 1 | 5.87 | 6.89 | 1 | 1 | 0 |
3 | Basti | Megha | 20023600 | NEDULA GP WSS | PHASE-2 | 1 | 1 | 1 | 1 | 1 | 11.05 | 10.41 | 1 | 1 | 0 |
4 | Basti | Megha | 20023746 | DAYALPUR GP WSS | PHASE-2 | 2 | 1 | 1 | 1 | 1 | 5.31 | 6.86 | 2 | 0 | 0 |
5 | Basti | Megha | 20023751 | MARAN GP WSS | PHASE-2 | 2 | 1 | 1 | 1 | 1 | 10.89 | 9.81 | 2 | 1 | 0 |
6 | Basti | VSA | 20032234 | JOGAPUR GP WSS | PHASE-3 | 3 | 1 | 1 | 1 | 1 | 6.33 | 6.33 | 3 | 3 | 0 |
7 | Basti | VSA | 20058893 | MALAHENI GP wss | PHASE-3 | 2 | 1 | 1 | 1 | 1 | 7.48 | 7.48 | 2 | 2 | 0 |
8 | Basti | VSA | 20059188 | PARWAR PARA GP wss | PHASE-3 | 3 | 1 | 1 | 1 | 1 | 7.63 | 7.63 | 3 | 3 | 0 |