Jal Jeevan Mission - District Dashboard  - Basti

       
Heirarchy / District Progress Reference
Total Block :
Total Panchayat :
Total Villages :
Population :
Households :
FHTC :
FHTC(%) :
Total HGJ Villages:
Total Certified :
Handed Over Villages :
GP level member :
VWSC/ Pani Samiti/ Water User Group :
Operation and Maintenance User :
Women identified for field test kit (FTK) testing :
Skilled Human Resources available in village :
UP Jal Nigam Old Scheme
Total Scheme :
Total Village :
Total OHT :
Schemes send to O&M Details
Total Scheme :
Total Village :
Total OHT :
Water Demand Daily(M3):
Water Demand Weekly(M3):
Water Demand Monthly(M3):
Water Supply Daily(M3):
Water Supply Weekly(M3):
Water Supply Monthly(M3):
Partial Complete Schemes Details
Total Scheme :
Total Village :
Total OHT :
Water Demand Daily(M3):
Water Demand Weekly(M3):
Water Demand Monthly(M3):
Water Supply Daily(M3):
Water Supply Weekly(M3):
Water Supply Monthly(M3):
Incoming Complaints/Feedback Received
All Complaints :
Close Complaints :
Pending Complaints :
Total Feedback Taken Details
Total Feedback Taken :
Satisfactory :
Partially Satisfactory :
Not Satisfactory:
Not Related to JJM :
Total Pradhan Call Feedback
All Complaints :
Close Complaints :
Pending Complaints :
Total Feedback Taken :
Satisfactory :
Partially Satisfactory :
Not Satisfactory:
Not Related to JJM :
S.E.,(Division), Jal Nigam (Rural) Feedback Taken
Total Feedback Taken :
Satisfactory :
Partially Satisfactory :
Not Satisfactory:
Not Related to JJM :
Chief Engineer, (Zone), Jal Nigam (Rural)
Total Feedback Taken :
Satisfactory :
Partially Satisfactory :
Not Satisfactory:
Not Related to JJM :
Chief Engineer, (H.O.), Jal Nigam (Rural)
Total Feedback Taken :
Satisfactory :
Partially Satisfactory :
Not Satisfactory:
Not Related to JJM :
Unit Co-ordinator (Technical), SWSM
Total Feedback Taken :
Satisfactory :
Partially Satisfactory :
Not Satisfactory:
Not Related to JJM :
Estimated Cost and Expenditure Details(In Lacs)
Estimated Cost :
Expenditure :
Expenditure(%) :
ISA Activities
Total ISA Activities :
Total Photos Uploaded :
Total Videos Uploaded :
IEC Activities
WorkShop/Wall Writing Activities :
PHASE II Activity :
IEC Regional Language Activity :
IEC Outdoor Activities :
JJM Scheme Details Phase 1       Phase 2,3,5       Phase 4
Total JJM Scheme :
Total JJM Scheme Covered Village :
O&M Schemes
O&M Schemes:
O&M JJM Village :
O&M Schemes Integrate With Automation :
Automation Integrated Schemes
Automation Installed Scheme:
Integrated Scheme :
Integrated OHT :
Integrated Village :
Live Connected OHT :
Live Pump On OHT :
Last 2 days Water Not Supply OHT :
Regular Water Supply OHT :
Water supply less than 75% percent :
Water supply greater than 150% percent :
Automation Integrated Verified Schemes (EE E&M)
Integrated Scheme :
Integrated OHT :
Integrated Village :
Functional OHT Water Demand/Supply (Meter 3)
Water Demand Daily :
Water Demand Weekly :
Water Demand Monthly :
Water Supply Daily :
Water Supply Weekly :
Water Supply Monthly :
Automation Integrated SchemesReference
Sno. Scheme Status Pump Status Scheme Id Scheme Name Agency Name Covered Village Regular Water Supply Last Data Receive Date
Total 20 20
1 20016704 BHIRWA GP WSS Megha 1 1 02-08-2025 12:12 PM
2 20017759 chanda buzurg Megha 2 2 02-08-2025 12:12 PM
3 20020466 SIKRA HAKEEM GP WSS Megha 4 4 02-08-2025 12:12 PM
4 20024110 MANAURAHI GP WSS Megha 2 2 02-08-2025 12:12 PM
5 20024467 KAITHWALIA GP WSS Megha 2 2 02-08-2025 12:12 PM
6 20024497 PAKRI CHANDA GP WSS Megha 1 1 02-08-2025 12:12 PM
7 20026473 KHAJURI URF BASGAV Megha 1 1 02-08-2025 12:12 PM
8 20032904 RUPGARH GP WSS VSA 2 2 02-08-2025 12:11 PM
9 20038776 RAMPUR GP WSS (B) Megha 3 3 02-08-2025 12:12 PM
10 20058893 MALAHENI GP wss VSA 2 2 02-08-2025 12:11 PM
Components Wise Physical Progress
Sr.No. Components Target Achivement %
1 2 3 4 5
1 Tubewell 858 841 98.02
2 Pump House 858 834 97.20
3 Chlorination system 624 615 98.56
4 OHT 854 818/329 95.78
5 Distribution (Line Laying in Km.) 8353 8050 96.37
6 Solar Plant 851 780 91.66
7 F.H.T.C. 359777 341866 95.02
9 ROAD DISMENTLING/RESTORATION(KM) 1837 1775 96.62
10 Villages where 100 % road restoration completed 97070 60333 62.15
11 Comissioning of Village 2528 1742 68.91
12 Regular water supply 2528 1303 51.54
Agency Progress Details
Sr.No. Agency No Of Scheme No Of Village households FHTC FHTC % Har Gar Gal Certified
1 2 3 4 5 6 7 8 9
1 JAKSON - VISHVARAJ (JV) 103 326 32140 28434 88.47% 40 2
2 Megha 673 1900 213853 202629 94.75% 841 55
3 VSA 80 302 31605 30040 95.05% 153 71
Total 856 2528 277598 261103 94.06% 1034 128